Claire Estates

A complex renovation brought through completion and occupancy after a delivery-team change, incomplete work, limited documentation, unresolved selections, and out-of-sequence construction.

Project type: Complex renovation
Asynco role: Construction Manager
Completion: November 26, 2024

Location: Downtown Edmonton
Client / owner: ??

When Asynco entered Clair Estates, the project was already in motion and had experienced a delivery-team change. The renovation included varied levels of completion, limited documentation, incomplete work, unresolved selections, and construction activity that was not fully aligned in sequence.

This was not a clean handoff. It was the kind of project where the next phase depended on first understanding what was actually complete, what remained unresolved, what decisions still needed to be made, and how to bring the work back into a manageable structure.

As construction manager, Asynco stepped in to bring clarity, documentation, coordination, and completion discipline to the project.

Asynco’s work included:

  • Assessing existing project conditions
  • Identifying incomplete and unresolved work
  • Establishing documentation and tracking
  • Developing a practical completion plan
  • Coordinating remaining construction activity
  • Working with the owner and tenant on interior design and finish selections
  • Supporting sequencing and coordination through the remaining work
  • Carrying the project through completion and occupancy

The project needed structure before it could regain momentum.

The key challenge was not simply finishing a checklist. The project required Asynco to make sense of varied completion levels, limited documentation, unresolved selections, and work that needed to be brought into a more controlled sequence.

In a project like this, missed details can create delays, confusion, duplicated effort, and frustration for the owner, tenant, and delivery team. Asynco’s role was to stabilize the path forward and help the remaining work move with clearer coordination.

From unclear handoff to managed completion.

Asynco began by assessing the project’s actual condition and identifying what remained incomplete. From there, Asynco established documentation and tracking so the work could be understood, assigned, monitored, and advanced.

The completion plan gave the project a clearer path. Asynco coordinated the remaining work, helped resolve open selections with the owner and tenant, and supported the project through the final stages required for completion and occupancy.